The supply gap in some critical metals is real. It is not the same for every metal, and a long-term outlook is not a description of today's market. But for copper, and for lithium, official outlooks still see a deficit through the next decade.
The usual response is to look for more deposits. That is not where I see smaller mines getting stuck. The rock is often already in a study. What stalls the project is capital, power and infrastructure. A study is not a mine. Announced capacity is not production.
Is there a critical minerals supply deficit?
For some metals, yes. For others, the picture is milder.
The International Energy Agency's Global Critical Minerals Outlook 2026 says supply deficits for copper and lithium are set to persist through 2035, even though the outlook has improved as new projects advance. For copper, the IEA cut the projected deficit in 2035 from around 30% in the previous Outlook to 25%. GEM Mining Consulting, reading the same IEA outlook, put expected copper supply at 75% of requirements in 2035, and treated lithium as short on volume as well.
Nickel is not in the same place. The IEA's base case still shows a slight supply gap, but it also notes a host of early-stage projects that could cover demand if they come online as scheduled. I will not treat nickel as if it faced the same shortage as copper.
A deficit in an outlook is also not a tonne in the ground today. The IEA figures rest on announced projects. If those projects slip, the gap stays open for longer.
Is the problem a lack of deposits?
No. The constraint is the time and the cost of turning a deposit into a working mine.
The USGS 2026 mineral commodity summary shows world copper reserves far above a year's mine output, and a much larger identified resource behind those reserves. The IEA's 2026 outlook still sees a copper deficit after counting announced projects. That is a development problem, not a missing-deposit problem. GEM, writing on the same outlook, put it plainly: reserves alone are not supply. The metal still has to be financed, permitted, mined and delivered.
That is why a long list of junior studies does not close a deficit. I would not add proposed capacity as though it were production.
Why do small mines stall between study and production?
Because the hard part often starts after the study.
The IEA's analysis of major mines that began operating between 2010 and 2019 found that it takes more than 16 years, on average, to go from discovery to first production. S&P Global, in a study of 127 precious and base metal mines that started between 2002 and 2023, found an average of 15.7 years for the same span. Those figures cover the whole path, from discovery through exploration, studies and construction. They are not a clock that starts on the day the feasibility study is filed.
What they do show is that a long wait sits in the middle of the path. S&P recorded nickel cases in which the wait after the feasibility study was lengthened by trouble raising capital, by changes of ownership, or both. A smaller company feels that squeeze more than a major. The pit, the mill and the debt already compete for scarce cash. Roads, water and a grid connection, if they are needed, add more capital before the first tonne is sold.
The World Bank has warned that when power and transport are built for one project at a time, costs rise and smaller operators are shut out. The IEA, writing about Latin America's chance to add supply, points to high financing costs and infrastructure gaps in power and water. Multilateral development banks, in a joint statement in April 2026, put quality infrastructure, including power, transport and water, at the heart of getting critical-mineral projects built.
A smaller mine can be a useful source of supply before a major new project starts shipping. An expansion at an existing mine is worth examining alongside a new large pit. Neither deserves a free pass on costs, permits or delivery risk, and neither should be counted as metal until it is financed and built.
Where does power fit when a smaller mine tries to reach production?
It is one of the costs that can stall the project, especially off a strong grid.
Many smaller mines sit far from a reliable connection, or on a grid that cannot be counted on. The usual fallback is diesel. That fuel is costly to haul, and its price moves around. The bill competes with the pit and the mill. For what solar and batteries replace on a diesel site, and what they do not, see Replacing diesel generators at a remote mine with solar and batteries. Copper, nickel and lithium mines that have already added hybrid plants are covered in Solar and batteries for copper and other critical-metal mines.
The mine does not have to fund the power plant itself. Under a power purchase agreement, or PPA, a power company funds, owns and runs the solar and battery plant. The mine provides land and buys the electricity. GoSí Energy offers mines a Land + PPA model. The mine provides land near the power station. GoSí coordinates the work. EPC partners design, build and install the plant. The mine buys the power.
That does not make the project easy. Lenders still have to be satisfied that the mine can pay for the power over a term the ore can support. Those tests are set out in How a smaller mine finances a solar and battery plant. I will not repeat them here. Power is not the only constraint, and a PPA does not remove the need for backup engines or a later grid connection. It can, however, keep the energy plant off the mine's own balance sheet, so more of the scarce capital can go into the pit and the mill.
FAQ
Is there a critical minerals supply deficit?
For copper and lithium, the IEA still sees a deficit through 2035. Nickel is milder. A long-term outlook is not a picture of today's market.
Why do small mines stall between study and production?
Often because capital, power and infrastructure are not in place after the study. A study is not a mine, and announced capacity is not production.
Do smaller mines lack the deposits to close the gap?
No. Official reserve and resource figures, and the IEA project pipeline, point to a development problem, not a missing-deposit problem.
Can a smaller mine get power without funding the plant?
Yes, under a PPA a power company funds and owns the plant and the mine buys the electricity. The contract still has to be financeable. That is covered in the earlier article on how a smaller mine finances solar.
If you want a first screening of whether a Land + PPA could fit a site that is stalled on power, you are welcome to send a year of fuel or power bills, and a note on remaining mine life, through our contact page.
More insights
Solar and batteries for copper and other critical-metal mines
Why copper, nickel and lithium mines are adding solar and batteries, including off-grid plants, and what a Land + PPA changes for the operator.
Solar and batteries for copper and other critical-metal minesHow a smaller mine finances a solar and battery plant
How a smaller mine can buy solar power under a PPA without funding the plant, and what lenders and developers need before the deal closes.
How a smaller mine finances a solar and battery plantReplacing diesel generators at a remote mine with solar and batteries
How a remote mine cuts diesel with solar and batteries: what panels replace, what the battery adds, how to size it and how to pay for it.
Replacing diesel generators at a remote mine with solar and batteriesSolar and battery plants for remote gold mines
What three working gold mines show about solar, wind and batteries off the grid, and what a study for your own mine needs.
Solar and battery plants for remote gold minesBattery storage for mines: what the battery does, and how big it should be
What a battery does at a mine, power vs energy in plain words, and how to size it. Real cases: Agnew, Fekola, Bellevue.
Battery storage for mines: what the battery does, and how big it should be