A junior or mid-tier mine often cannot put scarce capital into a power plant. The pit, the mill and the debt come first. That does not mean the site has to keep buying all of its power as diesel.
Under a power purchase agreement, or PPA, a power company funds the solar and battery plant. It owns the plant and runs it. The mine buys the electricity. The mine does not have to pay for the plant itself.
Can a smaller mine get a solar plant without paying the capex?
Yes, if the contract can be financed. That test is stricter for a smaller miner than for a major.
At Sandfire's DeGrussa copper-gold mine in Western Australia, the mine bought power from a plant it did not own. The first PPA ran for 5.5 years, was extended when the mine outlasted its planned 2021 closure, and ended when mining stopped in October 2022. The Clean Energy Finance Corporation and Engineering & Mining Journal both record that sequence. Gold Fields buys power at Agnew under a 10-year agreement with EDL, which owns and operates the plant.
GoSí Energy offers mines a Land + PPA model. The mine provides land near the power station. GoSí coordinates the work. EPC partners design, build and install the plant. The mine buys the power. For what solar and batteries replace on a diesel site, see Replacing diesel generators at a remote mine with solar and batteries.
What makes a mine solar PPA bankable?
Lenders look at one main revenue stream: the mine's payments under the PPA. If those payments are not reliable, the plant does not get built on borrowed money. The World Bank's guide to power purchase agreements, and the standard list of bankable PPA features used by development finance agencies, both start from that point.
The offtaker has to be creditworthy, or backed by someone who is. The term has to be long enough for the debt to be repaid, but not longer than the mine can honestly support. The tariff has to be clear enough that lenders can model it. And if the mine stops paying, or closes early, a security package has to cover the unpaid debt. The ore will run out. A PPA that ignores that is hard to finance well.
What do lenders ask of a junior or mid-tier miner?
A junior or mid-tier company is not shut out, but the credit question is sharper than it is for a major.
If the mine company is not strong enough on its own, lenders typically ask for extra support: a parent company guarantee, a letter of credit, a short-term liquidity facility, or another form of payment security. The World Bank notes that when the offtaker is not creditworthy enough, lenders require broader credit support.
They will also look at the mine plan. In "Beware of a Contract That Could Outlive the Ore" (Engineering & Mining Journal, November 2026, pp. 30-31), I argued that the term should sit inside the life defended before the board on proven and probable reserves, not inside the resource story told to investors. A short reserve life makes a long PPA harder to close, or more expensive, or both.
How long should the PPA run against the mine life?
A producer recovers its capital over the term. A shorter contract usually means a higher price per megawatt-hour. The temptation is to sign long to bring that price down. Resist it unless the reserves support it.
Alignment between remaining mine life and the PPA is the main commercial question. juwi made that case in Mining Weekly. I made the same point in E&MJ: if an extension is likely, write it in as an option the mine holds. DeGrussa did that. The first term was short, then extended, and the contract ended with the ore.
Western Australia's Hybrid Power Purchase Agreement Guide also builds in a buyout if the agreement ends early, and an option to extend if the mine lasts longer. Fit the term inside a defensible mine life, long enough to repay the debt, with an extension option and a clear exit.
What security do lenders and developers ask for?
Take-or-pay is the form lenders like most. The mine pays for a set amount of energy or capacity, whether it uses it or not, to cover the producer's fixed costs and debt service. Treat it as a firm cost, like a lease. Do not sign it for a volume you cannot defend if the mill is down or the grade falls.
If the mine closes early, someone owns a power plant with no customer. The contract should set an early-termination payment that falls as capital is repaid, give the mine the right to buy the plant, and say who removes the equipment and rehabilitates the ground. I suggested reading that clause first in the E&MJ article. The Western Australian guide takes the same view.
Lenders will also want the PPA assigned to them as security, with notice of default, time to cure it, and step-in rights, usually in a direct agreement. Bank guarantees often back the mine's obligations. They are not a substitute for a mine life that fits the term.
Do the diesel engines or the grid still have to be there?
Yes. A PPA for solar and batteries does not remove the need for backup. A processing plant that loses power loses production. Underground ventilation cannot wait for the sun.
DeGrussa's solar plant was integrated with an existing diesel power station. Agnew kept a gas and diesel station behind the renewables. The plants in the E&MJ article all kept their engines. The battery has its own job, covered in Battery storage for mines. It does not replace a plan for long cloudy spells, maintenance or a grid outage. If the mine is on the grid, the contract still has to say who bears the risk of connection and transmission. See also Solar and battery plants for remote gold mines.
FAQ
Can a junior miner finance a solar plant with a PPA, without capex?
Yes, if the PPA is bankable. The power company funds the plant and the mine buys the power.
What if remaining mine life is shorter than a typical PPA?
Do not sign a term the reserves cannot support. Use a shorter first term with an extension option, and agree the buyout before you sign.
What is take-or-pay, and should a smaller mine agree to it?
It means paying for a set volume or capacity whether you use it or not. Lenders often need some form of it. Agree only to a volume you can defend if the mill is down.
Will a solar and battery PPA let the mine retire its diesel generators?
Not completely. Engines or a grid connection almost always stay as backup.
If you want a first screening of whether a Land + PPA could fit your site, you are welcome to send a year of fuel bills, and a note on remaining mine life, through our contact page.
More insights
Why smaller miners are not closing the critical-metals gap
The critical-metals gap is real, but capital, power and infrastructure, not a lack of deposits, keep smaller mines from adding supply.
Why smaller miners are not closing the critical-metals gapSolar and batteries for copper and other critical-metal mines
Why copper, nickel and lithium mines are adding solar and batteries, including off-grid plants, and what a Land + PPA changes for the operator.
Solar and batteries for copper and other critical-metal minesReplacing diesel generators at a remote mine with solar and batteries
How a remote mine cuts diesel with solar and batteries: what panels replace, what the battery adds, how to size it and how to pay for it.
Replacing diesel generators at a remote mine with solar and batteriesSolar and battery plants for remote gold mines
What three working gold mines show about solar, wind and batteries off the grid, and what a study for your own mine needs.
Solar and battery plants for remote gold minesBattery storage for mines: what the battery does, and how big it should be
What a battery does at a mine, power vs energy in plain words, and how to size it. Real cases: Agnew, Fekola, Bellevue.
Battery storage for mines: what the battery does, and how big it should be